Project Overview
The Ethiopia 20MW Data Mining Farm project required reliable medium-voltage power infrastructure to support continuous, energy-intensive computing operations. The facility demanded robust equipment capable of delivering stable power under sustained load conditions while supporting future scalability.
Our Role
Emirates Panel was engaged to supply key medium-voltage power components forming part of the facility’s primary electrical infrastructure. The scope focused on correct specification, reliability, and alignment with project timelines for seamless installation.
Scope of Supply
Medium-voltage transformers for primary power distribution
Medium-voltage cables for power transmission and connectivity
Technical documentation and coordination support
Challenges & Solutions
Data mining facilities require stable MV systems to ensure uninterrupted operation and equipment protection. Emirates Panel ensured proper transformer sizing, cable specification alignment, and coordinated delivery to support efficient on-site integration.
Outcome
The supplied MV transformers and cables enabled stable and reliable power distribution across the 20MW data mining facility. Emirates Panel’s contribution supported operational continuity and long-term infrastructure performance.
Project Highlights
MV transformers and cables supplied
20MW high-capacity data mining infrastructure support
Invoiced and delivered in September 2025
Reliable supply coordination for energy-intensive operations